12 King Street Cat B Fit Out

Client: Opus North

Sector: Commercial (Refurbishment/ Fit Out)

Services: Project Management, Employers Agent

Project Summary: Following the successful completion of the 7 Storey Kings Street Refurbishment, Opus North further commissioned Peak PM for the landlord fit out works. The commission comprises FFE Installation to the 7th floor executive lounge and external balcony, along with ground floor lobby areas which include the installation of speed gate access for personnel, encompassing smart building features. Peak PM have collaborated with Leeds based designers, DLA Architecture for design proposals, also Design Tonic as the clients’ preferred installation contractor. Infrastructure for the speed gate installation has been installed by GMI during the refurbishment phase.
Key Milestone: Works completed within a 5 week duration, including all fit out and speed gate commissioning.