5-7 Main Street, Grassington

Client: Private

Sector: Residential

Services: PEAK were appointed as Project Manager, Contract Administrator and Cost Consultant.

Project Summary: Ashfield Group commenced works in November 2021 to demolish the existing shop lean-to extension before excavating to facilitate the larger extension, with first floor flat extension and refurbishment works undertaken concurrently. The property is sandwiched between two listed buildings with the proposed works notifiable under the Party Wall Act. The shop remained open 7 days a week for nearly all the contract period, only closing for 4 days so the shop could be fitted out and shelves stocked. Bowman Riley were appointed as lead designer, working with Holdgate Consulting for Civil & Structural design.
Key Milestone: Works completed June 2022.