Providence Park, Keighley

Client: Modern Equipment & Foundry Engineering Ltd

Sector: Industrial

Services: Project Management, Employer’s Agent and Cost Consultant

Project Summary: This project comprised construction of 37,000ft² high-quality industrial space, an 8,750ft² educational building to Department of Education standards, an A3 unit and associated services. The development includes 4no. trade counter units, 17no. smaller light industrial units with the flexibility to amalgamate units with 81no. car parking spaces and landscaping. The site was previously occupied by Northern Gas Networks and a steel foundry and more historically terraced housing with deep basements. An extensive demolition and site remediation package was undertaken prior to commencement of the main works. Salt Architects and CGP M&E Consulting Engineers were appointed with the Main Contractor Rock Structural undertaking the role of Civil & Structural Engineer. The works were undertaking using a JCT Design & Build Contract.
Key Milestone: Works commenced on site in April 2023 and completed in February 2025.