Project Summary: PEAK were appointed by Sutcliffe Construction to provide Contract Management services with works being delivered under a JCT Design & Build Contract incorporating bespoke schedule of amendments. Duties included monthly reporting advising on Construction progress, assisting on commercial management including change control and financial reporting.
Works comprised the construction of 12no. Industrial units and refurbishment/conversion of existing stone barn to office accommodation. New build works were a combination of steel portal frame units along with load bearing construction. Complexities on site included the proximity of the adjacent railway lines and tight planning controls working within the Yorkshire Dales National Park.
Campbell Driver Partnership Architects were appointed as lead designer working with Paul Wates Group Civil & Structural Engineers. Michael Eyers Partnership were appointed as Project Manager, Employers Agent and Cost Consultant.